Question 121

The team member collating the list of customers has now forecast that it will NOT be complete by the end of
this stage as originally planned, due to a number of new prospective customers' details not yet being available.
What action should the team member take?
  • Question 122

    Who sets the tolerances for a work package?
  • Question 123

    During Executing a Work package, specialist products are created and quality reviews are carried out - which management product captures the details of these reviews?
  • Question 124

    Who is responsible for committing user resources to the project?
  • Question 125

    Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk
    management strategy?