Question 116

According to PRINCE2, which statement about appointing the MFH Quality Manager to administer the
configuration management procedure is correct?
  • Question 117

    Which statement is an appropriate entry for the project approach heading within the Project Brief?
  • Question 118

    HOTSPOT
    Scenario:
    Techniques, processes and procedures
    1. Any threat that may result in a loss of MFH data must be escalated immediately.
    Joint agreements
    2. Work is to start at the beginning of week 2 (Stage 4).
    3. The project will take two years to complete, at an estimated cost of £2.5m.
    Tolerances
    4. None.
    Constraints
    5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
    6. Installation work must take place during MFH normal working hours.
    7. +£10,000 / -£25,000.
    Reporting arrangements
    8. Highlight Report every Monday by 10.00 am.
    9. The report must contain a summary of all products worked on during the previous week.
    10. Project Manager must be notified of any issues immediately by telephone.
    Problem handling and escalation
    11. Impact analysis of all issues must be completed within 24 hours.
    Extracts or references
    12. The Stage Plan for stage 4 is available from Project Support.
    Approval method
    13. Project Assurance will review the completed Work Package and confirm completion At the end of stage 3, the service provider will be selected and the contract awarded. During stage 4, the Account Manager for the selected service provider will work with the Project Manager to complete the transition of the services to the selected service provider.
    Hot Area:

    Question 119

    Which 2 statements should be recorded under the Timescale heading?
  • Question 120

    Scenario
    Additional Information
    Extract from the Communication Management Strategy.
    The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

    Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
    The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
    After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
    There is no mention of any Stage Plans, yet there are two further stages proposed. How will this be resolved?