Question 146

Scenario
Extract from the Project Product Description (with errors)

Which 2 statements apply to the Customer's quality expectations section?
  • Question 147

    While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend.
    Which option is an appropriate Change Authority for the Outsourcing project?
  • Question 148

    PLANS
    During the initiation stage, the project manager is creating the project plan.
    Here are three activities carried out as part of PRINCE2's recommended approach to planning.
    As part of which step of the approach (A-F) should each activity be carried out?
    Choose only one step for each activity. Each step can be used once, more than once, or not at all.

    Question 149

    It is now late October and the project is in stage 3. The label design competition has been held and the photos of the staff have been taken. The CEO and Marketing Director still need to choose the winning label design and the 12 photos for the calendar. However, the Executive has learned that two competitors are issuing calendars to MNO's customers by the middle of November. After analyzing the impact of this Issue, one of the options the Project Manager has presented to the Project Board is to close the project prematurely.
    There are a number of key facts relating to this project that would need to be recorded if the project Y-e to be closed now.
    Which product should show that without the calendar the company is going to experience difficulties recovering its decline in orders, and alternative solutions are required if the company is going to recover its position?
  • Question 150

    Which 2 statements should be recorded under the Timescale heading?