Question 16

Which of the following is not part of the composition of a Plan?
  • Question 17

    During the 'create the project plan' activity as part of the initiation stage, the project manager identifies several threats to the project timescales. These threats relate to stage 3 products. Therefore, the project manager decides to wait until the end of stage 2 to assess the risks to the project plan.
    Is this an appropriate application of the plans theme, and why?
  • Question 18

    In which strategy would the change control process be recorded?
  • Question 19

    Additional Information
    A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff. This meeting should have occurred by now.
    The Engineering Manager was made aware of this requirement but when asked he reported that he has received no communication from the photographer. The Project Manager has tried to call the photographer and has had no response. The Project Manager believes there is a risk that Portraits Ltd are overbooking work and prioritizing other clients' work. If Portraits ltd do not deliver on schedule the project will be delayed and the expected benefits will be reduced.
    The contract is to be reviewed and Portraits Ltd reminded of their agreement.
    The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar, thereby reducing the anticipated benefits of the Calendar project.
    Column 1 contains a number of risk responses identified by the Project Manager following an assessment of this risk. Column 2 contains a list of threat response types. For each risk response in Column 1, select from Column 2 the type of response it represents. Each option from Column 2 can be used once, more than once or not at all.
    Drop down the right answer.

    Question 20

    Scenario:
    Techniques, processes and procedures
    1. Any threat that may result in a loss of MFH data must be escalated immediately.
    Joint agreements
    2. Work is to start at the beginning of week 2 (Stage 4).
    3. The project will take two years to complete, at an estimated cost of £2.5m.
    Tolerances
    4. None.
    Constraints
    5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
    6. Installation work must take place during MFH normal working hours.
    7. +£10,000 / -£25,000.
    Reporting arrangements
    8. Highlight Report every Monday by 10.00 am.
    9. The report must contain a summary of all products worked on during the previous week.
    10. Project Manager must be notified of any issues immediately by telephone.
    Problem handling and escalation
    11. Impact analysis of all issues must be completed within 24 hours.
    Extracts or references
    12. The Stage Plan for stage 4 is available from Project Support.
    Approval method
    13. Project Assurance will review the completed Work Package and confirm completion.
    Which 2 statements apply to either the Development Interfaces or Operations and maintenance interfaces sections?
  • Premium Bundle

    Newest PRINCE2-Practitioner Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PRINCE2-Practitioner Exam! BraindumpsPass.com now offer the updated PRINCE2-Practitioner exam dumps, the BraindumpsPass.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PRINCE2-Practitioner pdf dumps with Exam Engine here:

    (285 Q&As Dumps, 40%OFF Special Discount: Exam-Tests)
    Other Version
    1085PRINCE2.PRINCE2-Practitioner.v2024-03-28.q141
    2427PRINCE2.PRINCE2-Practitioner.v2022-09-05.q130
    4320PRINCE2.PRINCE2-Practitioner.v2022-01-15.q133
    Latest Upload
    107Oracle.1Z0-1057-23.v2025-09-10.q47
    146Google.Professional-Cloud-Network-Engineer.v2025-09-09.q179
    131SAP.C-S4EWM-2023.v2025-09-08.q83
    155TheSecOpsGroup.CNSP.v2025-09-08.q20
    204CFAInstitute.ESG-Investing.v2025-09-08.q173
    152PECB.ISO-IEC-27001-Lead-Implementer.v2025-09-06.q132
    140Salesforce.Data-Architect.v2025-09-05.q216
    136Adobe.AD0-E605.v2025-09-05.q50
    176Nutanix.NCP-MCI-6.10.v2025-09-05.q55
    114Oracle.1z0-591.v2025-09-05.q104