Question 6

Scenario
Additional Information
Extract from the Communication Management Strategy.
The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
What statement applies to the Records section?
  • Question 7

    MANAGING A STAGE BOUNDARY
    The ABC Company trainers have been accredited and the course booking procedures have been amended. The 'managing a stage boundary' process is taking place at the end of stage 3.
    Which activity should occur during the 'update the business case' activity?
  • Question 8

    One of the senior managers of the company that is developing the 'e-learning course' has worked with ABC Company before. The team manager for the delivery of the 'e-learning course' has looked on ABC Company's intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to discuss this project.
    Is this an appropriate application of the 'learn from experience' principle, and why?
  • Question 9

    Scenario
    Additional Information
    Extract from the Communication Management Strategy.
    The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

    Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
    The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
    After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
    This question provides a number of changes which may or may not be required to the Extract from the Communication Management Strategy provided in the additional information.
    Which statement applies to the Stakeholder analysis: Interested parties section?
  • Question 10

    Who is responsible for ensuring that the value-for-money solution is constantly reassessed?
  • Premium Bundle

    Newest PRINCE2-Practitioner Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PRINCE2-Practitioner Exam! BraindumpsPass.com now offer the updated PRINCE2-Practitioner exam dumps, the BraindumpsPass.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PRINCE2-Practitioner pdf dumps with Exam Engine here:

    (285 Q&As Dumps, 40%OFF Special Discount: Exam-Tests)
    Other Version
    1085PRINCE2.PRINCE2-Practitioner.v2024-03-28.q141
    3686PRINCE2.PRINCE2-Practitioner.v2022-06-08.q175
    4326PRINCE2.PRINCE2-Practitioner.v2022-01-15.q133
    Latest Upload
    107Oracle.1Z0-1057-23.v2025-09-10.q47
    146Google.Professional-Cloud-Network-Engineer.v2025-09-09.q179
    131SAP.C-S4EWM-2023.v2025-09-08.q83
    155TheSecOpsGroup.CNSP.v2025-09-08.q20
    204CFAInstitute.ESG-Investing.v2025-09-08.q173
    152PECB.ISO-IEC-27001-Lead-Implementer.v2025-09-06.q132
    140Salesforce.Data-Architect.v2025-09-05.q216
    136Adobe.AD0-E605.v2025-09-05.q50
    176Nutanix.NCP-MCI-6.10.v2025-09-05.q55
    114Oracle.1z0-591.v2025-09-05.q104