Question 101

Scenario
Extract from the Project Product Description (with errors)

Which 2 statements apply to the Composition section?
  • Question 102

    HOTSPOT
    Scenario
    A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:
    Do nothing.
    Re-engineer selected business functions.
    Outsource selected business functions.
    The feasibility study concluded that there was a case for outsourcing the MFH Information Technology
    Division and the Facilities Division (maintenance of buildings and grounds). The recommendations were:
    One service provider should be contracted to provide the services currently provided by the
    Information Technology Division and the Facilities Division.
    A 10-year service contract should be agreed with the selected service provider.
    The feasibility study developed high-level designs of the current organization, processes, systems and
    operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:
    Use PRINCE2.
    Set up the project with 4 management stages:
    Stage 1. Standard PRINCE2 initiation activities.
    Stage 2. Create detailed designs (future organization, processes, systems and operating
    models) and the service level agreement between MFH and the future service
    provider.
    Stage 3. Request and evaluate proposals, select service provider and agree contract.
    Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run
    trial period.
    Initial estimates indicated that the project would cost (GBP)2.5m and take two years to complete.
    MFH senior management agreed that there was a case for outsourcing, and accepted the
    recommendations as a basis for the project. There is an expected saving of (GBP)20m over 10 years.
    The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs.
    Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

    Question 103

    A quality review of the 'marketing materials' has started. The team manager for the 'marketing materials' has been unhappy with the team's workload throughout the project and refuses to attend the review meeting to present the material. The team manager suggests that a new marketing team member make the presentation.
    However, the chair decides to represent the marketing team and makes a list of actions to resolve later.
    Is this an appropriate approach to the quality review, and why?
  • Question 104

    Scenario
    Additional Information
    Extract from the Communication Management Strategy.
    The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document.

    Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board.
    The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined the Starting Up a Project process and the Initiating a Project process. No Project Brief has been produced. Instead the Project Manager used the project mandate to produce a simple Project Initiation Documentation (PlO). The PlO includes the Business Case, a product checklist and several Product Descriptions, Including the Project Product Description. Short sections are also included for each of the strategies and the controls to be applied. The Project Manager has elected to use the Daily Log to record all risks, issues, lessons and quality - results.
    After the initiation stage there will be two further stages during which a small number of Work Packages will be authorized. While these are being managed, the Project Manager will hold regular checkpoints, which will support the production of weekly Highlight Reports to the Project Board.
    No Benefits Review Plan has been developed. Where should the schedule of benefit reviews be recorded?
  • Question 105

    The project is now in stage 2. The Project Manager has heard about the possibility of a competitor also
    producing a calendar to be delivered earlier than the target date for this project. There is a threat that the early
    release of a competitor's calendar may weaken the impact of the MNO Manufacturing Company calendar,
    thereby reducing the anticipated benefits of the Calendar project.
    Which 2 statements should be recorded under the Risk tolerance heading?
  • Premium Bundle

    Newest PRINCE2-Practitioner Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PRINCE2-Practitioner Exam! BraindumpsPass.com now offer the updated PRINCE2-Practitioner exam dumps, the BraindumpsPass.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PRINCE2-Practitioner pdf dumps with Exam Engine here:

    (266 Q&As Dumps, 40%OFF Special Discount: Exam-Tests)
    Other Version
    2502PRINCE2.PRINCE2-Practitioner.v2024-03-28.q141
    3227PRINCE2.PRINCE2-Practitioner.v2022-09-05.q130
    4622PRINCE2.PRINCE2-Practitioner.v2022-06-08.q175
    5131PRINCE2.PRINCE2-Practitioner.v2022-01-15.q133
    Latest Upload
    175NAHQ.CPHQ.v2026-09-03.q481
    113SAP.C-S4CPB-2602.v2026-09-02.q7
    109Cisco.700-805.v2026-09-02.q86
    161MSSC.CLT-4.0.v2026-09-02.q43
    126Fitness.NCSF-CPT.v2026-09-02.q18
    174Google.Generative-AI-Leader.v2026-09-02.q77
    139PECB.ISO-14001-Lead-Auditor.v2026-09-01.q39
    126Google.GCP-DE.v2026-09-01.q27
    161Cisco.300-820.v2026-09-01.q105
    154Cisco.500-220.v2026-09-01.q72