Question 36

The Calendar project was delivered as originally planned, and Is now preparing for planned closure.
Lines 1 to 6 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies. Each option can be used once, more than once or not at all.

Question 37

During a work package the Team manager needs to keep the project manager informed, which management product is used for this?
  • Question 38

    HOTSPOT
    Scenario:
    Techniques, processes and procedures
    1. Any threat that may result in a loss of MFH data must be escalated immediately.
    Joint agreements
    2. Work is to start at the beginning of week 2 (Stage 4).
    3. The project will take two years to complete, at an estimated cost of £2.5m.
    Tolerances
    4. None.
    Constraints
    5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment.
    6. Installation work must take place during MFH normal working hours.
    7. +£10,000 / -£25,000.
    Reporting arrangements
    8. Highlight Report every Monday by 10.00 am.
    9. The report must contain a summary of all products worked on during the previous week.
    10. Project Manager must be notified of any issues immediately by telephone.
    Problem handling and escalation
    11. Impact analysis of all issues must be completed within 24 hours.
    Extracts or references
    12. The Stage Plan for stage 4 is available from Project Support.
    Approval method
    13. Project Assurance will review the completed Work Package and confirm completion Column 1 is a list of actions that occur during the Controlling a Stage process. For each action in Column
    1, select from Column 2 the PRINCE2 theme that is being applied. Each selection from Column 2 can be used once, more than once or not at all.
    Drop down the answer from column 1 to column 2.
    Hot Area:

    Question 39

    A concern about possible subsidence damage has been recorded as an issue.
    Is this an appropriate application of the issues practice, and why?
  • Question 40

    Which 2 alternative actions apply to the proposed Senior Supplier for this project?
  • Premium Bundle

    Newest PRINCE2-Practitioner Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PRINCE2-Practitioner Exam! BraindumpsPass.com now offer the updated PRINCE2-Practitioner exam dumps, the BraindumpsPass.com PRINCE2-Practitioner exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PRINCE2-Practitioner pdf dumps with Exam Engine here:

    (266 Q&As Dumps, 40%OFF Special Discount: Exam-Tests)
    Other Version
    2502PRINCE2.PRINCE2-Practitioner.v2024-03-28.q141
    3227PRINCE2.PRINCE2-Practitioner.v2022-09-05.q130
    4622PRINCE2.PRINCE2-Practitioner.v2022-06-08.q175
    5131PRINCE2.PRINCE2-Practitioner.v2022-01-15.q133
    Latest Upload
    174NAHQ.CPHQ.v2026-09-03.q481
    113SAP.C-S4CPB-2602.v2026-09-02.q7
    109Cisco.700-805.v2026-09-02.q86
    161MSSC.CLT-4.0.v2026-09-02.q43
    126Fitness.NCSF-CPT.v2026-09-02.q18
    174Google.Generative-AI-Leader.v2026-09-02.q77
    139PECB.ISO-14001-Lead-Auditor.v2026-09-01.q39
    126Google.GCP-DE.v2026-09-01.q27
    160Cisco.300-820.v2026-09-01.q105
    154Cisco.500-220.v2026-09-01.q72