Question 66
Who determines how work is performed during the Sprint?
Question 67
What are two responsibilities of testers in a Development Team? (Choose two.)
Question 68
Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach.
A good way to continue is:
A good way to continue is:
Question 69
Which Scrum Values are exhibited by not building Product Backlog items that have low business value?
(Choose three.)
(Choose three.)
Question 70
Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose all that apply.)