Question 11
The Product Backlog is ordered by:
Question 12
True or False: A scrum Master Fulfills me same role as a traditional project Manager.
Question 13
When can a Development Team cancel a Sprint?
Question 14
Who does the work to make sure Product Backlog items conform to the Definition of Done?
(choose the Best answer)
(choose the Best answer)
Question 15
A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?