Question 1

At the Sprint Planning, the Development Team is not able to forecast the number of Product Backlog items it can do in the upcoming Sprint due to unclear requirements. The Product Owner, however, was able to clearly define the business objective he hopes to achieve in the Sprint.
Which of the following two actions would you support? (Choose two.)
  • Question 2

    A Scrum Team has been working on a product for several iterations and has an average velocity of 55 units of 'done' work per Sprint. A second team will be added to work on the same product.
    What might be the impact on the original team?
  • Question 3

    If burndown charts are used to visualize progress, what does a trendline through a release burndown chart indicate?
  • Question 4

    What action can the Scrum Master take to ensure communication between the Development Team and Product Owner is effective?
  • Question 5

    What is a Product Owner responsibility that he/she might delegate?