Question 66
A new member has just joined an existing Development Team that has been together for several Sprints. During the Sprint, the individual has been trying to share his ideas and viewpoints but is continuously ignored by the rest of the Development Team.
Which three Scrum Values has the Development Team been neglecting? (Choose three.)
Which three Scrum Values has the Development Team been neglecting? (Choose three.)
Question 67
Steven is a Scrum Master for three different teams building a single product from the same Product Backlog. Development Team members from each team have approached Steven complaining that their teams need Nicole, an external specialist, to commit full time for their next Sprint.
Which three acceptable solutions would Steven consider? (Choose three.)
Which three acceptable solutions would Steven consider? (Choose three.)
Question 68
A Scrum Team has been working on a product for several iterations and has an average velocity of 55 units of
'done' work per Sprint. A second team will be added to work on the same product.
What might be the impact on the original team?
'done' work per Sprint. A second team will be added to work on the same product.
What might be the impact on the original team?
Question 69
If burndown charts are used to visualize progress, what does a trendline through a release burndown chart indicate?
Premium Bundle
Newest PSM-II Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing PSM-II Exam! BraindumpsPass.com now offer the updated PSM-II exam dumps, the BraindumpsPass.com PSM-II exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com PSM-II pdf dumps with Exam Engine here: