Question 56

You have just been hired as a Scrum Master by a company new to Scrum. The company wants to use Scrum to build a new product that was conceived by the product management department.
You will be the Scrum Master of two new teams that will build a first version of the product. The product management department assigns two new Product Owners, but wants more advice about the required participation with the new Scrum Teams. Which two suggestions would you offer?
(Choose the best two answers)
  • Question 57

    How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?
  • Question 58

    User documentation is part of your Definition of Done. However, there are not enough technical writers for all teams. Your Scrum Team does not have a technical writer. What needs to be done?
    (choose the best answer)
  • Question 59

    Peter, the Product Owner, has been giving positive recognition to individual Development Team members who have moved their work to 'done' during the Daily Scrum. Peter wants to ensure the team is adhering to the ideal guideline on the burndown chart.
    What would be two valid actions for Steven, the Scrum Master, to take? (Choose two.)
  • Question 60

    You are the Scrum Master for four Scrum Teams working from the same Product Backlog.
    Several of the Developers come to you complaining that work identified for the upcoming two Sprints will require full time commitment from Stella, an external specialist who is not a member of any of the four Scrum Teams. What would you consider acceptable solutions for the problem?
    (Choose the best three answers)