Question 96

Scrum can be used to create new products, not to sustain or renew products.
  • Question 97

    In the Daily Scrum, the Scrum Master is not allowed to attend.
  • Question 98

    What is the main accountability (roles = outdated term) of a Project Manager in Scrum?
  • Question 99

    Each artifact contains a commitment. For the Sprint Backlog it is the Product Goal.
  • Question 100

    The Product Backlog has to be completed before the Sprint 0 can start.