Question 51
The Definition of Done is used to:
(choose the best three answers)
(choose the best three answers)
Question 52
Team A has a velocity of 50 with a Product Backlog of 140 points ordered by business value as perceived by stakeholders.
Delivery is expected in 6 Sprints. Will this project deliver the anticipated impact? (choose the best answer)
Delivery is expected in 6 Sprints. Will this project deliver the anticipated impact? (choose the best answer)
Question 53
A Product Owner is needed for every:
(choose the best answer)
(choose the best answer)
Question 54
What questions might the Developers use at the Daily Scrum? (choose the best three answers)
Question 55
Product A is a big revenue producer; it has:
. High Current Value and Low Unrealized Value.
Product B is a new product with a lot of potential; it has:
. Low Current Value and High Unrealized Value.
Using those two data points and taking a long-term view, which of the options below should you pursue?
(choose the best answer)
. High Current Value and Low Unrealized Value.
Product B is a new product with a lot of potential; it has:
. Low Current Value and High Unrealized Value.
Using those two data points and taking a long-term view, which of the options below should you pursue?
(choose the best answer)