Online Access Free PVIP Practice Test
| Exam Code: | PVIP |
| Exam Name: | PV Installation Professional (PVIP) Board Certification |
| Certification Provider: | NABCEP |
| Free Question Number: | 162 |
| Posted: | May 31, 2026 |
A 10 kW PV array uses 300W modules with a Voc of 40V and an Isc of 9A. The inverter has a maximum DC input of 600V and 25A. What is the maximum number of modules that can be connected in a single string?
When performing a system checkout after completing the installation, what is the SAFEST sequence of tasks to detect installation errors before closing any disconnects to the inverter, charge controller, or batteries?
A PV system includes a 15 kW array with a maximum power point voltage of 450V and current of 33.33A.
The inverter efficiency is 97%, and the AC output voltage is 240V. What is the AC output current under STC?
A tap conduct is to be connected to a feeder supplied by both a utility service source and a utility-interactive inverter source. The feeder utility source is a 400A breaker in a service panel, the inverter overcurrent protection device is rated at 100A, and the inverter continuous output current is 72. The tap conductor that is to be installed will be 17 ft. long. It will be located in a raceway and will supply a subpanel with a 50A main breaker.
What is the MINIMUM required ampacity of the tap conductor?