Question 6

A homeowner is weighing the PV module options for a roof-mounted solar array. Which is a correct option to present to the homeowner?
  • Question 7

    An installer was asked to provide a means to measure the voltage of each battery in a system. The bank is located 50 ft.
    From the data logger. The installer will be using shielded. Twisted pairs of instrumentation wiring, all run in the bundle a conduct.
    The signals are connected to isolated and ungrounded inputs at a data logger. Which safely precaution is MOST needed to protect the instrumentation wiring?
  • Question 8

    While surveying a potential three-phase project, an installer measures the voltage at the point of utility interconnection. The results are as follows:
    * Phase to phase: 240V
    * Phase A neutral: 120V
    * Phase B neutral: 208V
    * Phase C neutral: 120V
    Which is a likely cause of these reading?
  • Question 9

    When running horizontal 1-1/4 in, electrical metallic tubing (EMT) with compression fittings, what is the MAXIMUM permissible distance between condult supports?
  • Question 10

    A PV system was installed in July 2017 under the 2017 NEC. The system has a string inverter located inside a garage on a wall 10 ft, from the outside wall and 1oft, from the ac load center at the point of utility connection.
    The PV system has a PV array on the roof. Which of the following represents the PV rapid shutdown system requirement for the controlled PV system conductors associated with this PV array?