Question 191

Your health insurance company has set up its portfolio into five different categories: research and development, IT, Medicare, government health insurance, and non-government health insurance. Funding is allocated yearly to each of these six categories. As the portfolio manager at the enterprise level, you:
  • Question 192

    During a portfolio review meeting, the steering committee has decided on the inclusion of a new project to re-align the portfolio with its strategic objectives, what do you do before and after the meeting?
  • Question 193

    You are the manager for a governmental portfolio aiming to restructure the roads in your country. Having a tight schedule, a large number of stakeholders including the public, in addition to a strict budgeting framework, you know that you will be managing the performance closely and that the governance board and the stakeholders would want to check on the progress and performance frequently. For this you are developing a robust performance management plan. What can you use to help you start developing this plan?
  • Question 194

    As part of developing the Communication Management Plan, a portfolio manager executes the Communication Requirements Analysis, in addition to Stakeholders Analysis. Which of the following options in your opinion is a result of the Stakeholders Analysis?
  • Question 195

    As part of developing the Communication Management Plan, a portfolio manager executes the Communication Requirements Analysis, in addition to Stakeholders Analysis. Which of the following options in your opinion is a result of the Communication Requirements Analysis?