Question 141

You are the program manager of the HNG Program. This program has a budget at completion of $2,345,900 and is expected to last two years. The program is currently 30 percent complete and you have spent $789,000.
The program is supposed to be 35 percent complete but do to some delays you're slightly behind schedule.
Based on this information, what is the schedule variance (SV) of this program?
  • Question 142

    The above performance report shows the earned value (EV) analysis for a program. The program director performs a high-level analysis and must present a summary narrative to the steering committee.

    What do the current findings show?
  • Question 143

    What document asks the seller to provide your project with a detailed description of a project solution along with a price to complete the project work?
  • Question 144

    You are the program manager for the NHQ Program. Your program has a budget of
    $4,500,000 and has lasted for two years. Your program has just completed its final deliverable and you're completing the final program closure processes. What document must the program customer must now sign as part of program closure?
  • Question 145

    Program A is dependent upon program B to complete benefits sustainment for two benefits. Program A is on track to meet program benefits. However, program B's program manager has just advised that program B has been closed.
    What should program A's program manager update and review first with the stakeholders?