Question 51
The signal at the input to a balanced twisted pair cable is 10 mW. The cable is 1000 feet long and has an attenuation of 1 dB per 100 feet. This cable is connected to the input of a receiver. The noise level at the input to the receiver is 1 microwatt. What is the signal-to-noise ratio (SNR) (dB) at the receiver input?
Question 52
The CEC is revised every four years.
Question 53
The maximum vertical rise is the distance over which the cable is vertically self-supporting. This distance is a function of the weight of the cable and the:
Question 54
At the end of the second week of a project, the earned value (EV) of work is $8000 USd and the planned value (PV) of work is $7000 USd. What is true about the project?
Question 55
A campus backbone design linking two buildings requires that you install a high-fiber-count cable very quickly, using the conduit system provided. Cost is not so much an issue as urgency is to meet a service demand. Your first choice of fiber cable installation is to use: