Question 36

During which situations, the stakeholders might get concerned about the progress? (Choose all that apply)
  • Question 37

    Definition of Done is always same for Nexus and all individual Scrum Teams. True or False?
  • Question 38

    All the development team members need not attend Nexus Daily Scrum. True or False?
  • Question 39

    5 Scrum teams with 8 members each are working in a Nexus. They are struggling to create a DONE increment every Sprint. The scope is being adjusted often due to newly discovered dependencies and complications.
    Which techniques can be use to manage dependencies effectively? Select two best answers
  • Question 40

    How often should the Nexus Sprint Backlog be adjusted?