Question 16
In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting.
Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
Question 17
Identify three entities that must be set up in Oracle Manufacturing Cloud to create a Work Definition for an item that will be manufactured in-house.
Question 18
Identify the two configurations in Supply Chain cloud applications of Product Information Management (PIM) and Order promising (GOP), which must be set to process the Back-to-Back order with Make Supply Order, for a nonstocked item.
Question 19
Which two steps should you use to create a new Oracle Transactional Business Intelligence report in the Manufacturing Cloud?
Question 20
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.
Determine the available capacity of the resource R1 for that week.