Question 21
How much Total Float does drafting the product manual have?


Question 22
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?


Question 23
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
Question 24
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:


Question 25
The amount of time that an activity can be delayed from its early start date without delaying project completion is called