Question 36
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
Question 37
What is the remaining work duration of Active D?


Question 38
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
Question 39
Identify the minimum project duration.


Question 40
You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?