Question 36

Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
  • Question 37

    What is the remaining work duration of Active D?
  • Question 38

    When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?
  • Question 39

    Identify the minimum project duration.
  • Question 40

    You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?