Question 11
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?


Question 12
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
Question 13
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?


Question 14
Why does activity 1001 have two successor activities?


Question 15
Identify the minimum project duration.