Question 31

Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
  • Question 32

    What activities are concurrent to Activity 2001 in the "normal" schedule?
  • Question 33

    You are retained by a contractor who asks you to perform a simple as-planned versus as-built analysis (APAB) of a large hydro-electric dam project that took more than five years to complete. Your analysis will form the basis of a change order that requests a time extension. You suggest using a different methodology for quantifying the delay. Which of the following reasons for recommending a different analysis does NOT apply to a simple APAB analysis?
  • Question 34

    Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
  • Question 35

    In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?