Question 1
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?


Question 2
What was the original planned duration for Activity A through Activity G?


Question 3
What does the heavy, vertical line at "X" represent?


Question 4
The activity with the most total float is:


Question 5
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?