Question 36
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?


Question 37
Assumptions made during the planning stage should be_____________.
Question 38
If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?
Question 39
Determine the correct formula and date for the late finish for Activity 6002.
Question 40
Which of the following will always describe the critical path? The path with
