Question 21
The optimization team is planning their next 3-month experimentation roadmap for the homepage. They have the following candidates:
A - 8 weeks to build, another estimated A weeks to complete (run), and a projected 20% lift in conversion rate. B - 5 weeks to build, another estimated 7 weeks to complete (run), and a projected 25% lift in conversion rate. C - 5 weeks to build another estimated 3 weeks to complete (run), and a projected 15% lift in conversion rate. D - Requires no development team resource, an estimated 7 weeks to complete (run), and a projected 10% lift in conversion rate.
Providing all the estimations are correct and the development team can only build one test at a time, how should they plan their roadmap?
A - 8 weeks to build, another estimated A weeks to complete (run), and a projected 20% lift in conversion rate. B - 5 weeks to build, another estimated 7 weeks to complete (run), and a projected 25% lift in conversion rate. C - 5 weeks to build another estimated 3 weeks to complete (run), and a projected 15% lift in conversion rate. D - Requires no development team resource, an estimated 7 weeks to complete (run), and a projected 10% lift in conversion rate.
Providing all the estimations are correct and the development team can only build one test at a time, how should they plan their roadmap?
Question 22
As part of a large scale marketing campaign, an activity must run for 10 days. It will start at 3:00 am on a specific date and end 10 days later at 3:00 am. What is the easiest way to ensure this activity starts and ends automatically?
Question 23
An organization is tolling out a customer service chat that is available on the site Mondays through Fridays from 8:00 am to 5:00 pm. A lest will be conducted to determine how to optimize the link to the chat.
Which action enables an activity to be recurring every week during chat hours?
Which action enables an activity to be recurring every week during chat hours?