Question 1
All of the tasks on a project show as 100% complete, but when the Project Owner tries to update the status of the project to Complete, the Owner receives an error that reads "Project cannot be marked Complete if there are open issues and tasks that are not complete." How can the Project Owner determine which tasks are incomplete?
Question 2
A project manager compares the original schedule for a task to another set of dates that moved later after predecessors slipped and the assignee changed a completion commitment.
What do these later, system-calculated dates represent?
What do these later, system-calculated dates represent?
Question 3
A project manager has been asked to create a report showing the planned completion date for all the project manager's projects. The report must show results in a calendar view and all entries should be purple. What steps should the project manager take to create this view?
Question 4
A project manager needs to know the date that a task is likely to be finished based on the current progress of the task and its predecessors, regardless of any task constraints applied.
Which date type would the project manager utilize?
Which date type would the project manager utilize?
Question 5
Which field is used to create a milestone step on a milestone path in the Setup area?