Question 16
The last 5 tasks in a project need to happen within 10 days of the end of the project.
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
Which Task Constraint should the project manager use to configure this timeline without setting specific dates?
Question 17
A project manager checks an Incomplete Tasks report and notices that several tasks are listed even though the items are marked as 100% complete. What column can the project manager add to the view to understand why those tasks are included in the report?
Question 18
A project manager has assigned a task to a team. One of the members of the team wants to volunteer to complete the task.
Where would the volunteer navigate to do this?
Where would the volunteer navigate to do this?
Question 19
A company expects managers to complete a Workfront Business Case and submit it to the Project Sponsor for approval before a project enters Planning status.
What Workfront process will effectively facilitate the Project Sponsor review?
What Workfront process will effectively facilitate the Project Sponsor review?
Question 20
Taking into consideration any applied task constraints, a project manager needs to know the date that a task is likely to be finished based upon the current progress of the task and its predecessors. Which date type should the project manager utilize?