Question 36
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well.
Now, you increase the quantity of the external activity. How does the system support this scenario?
Now, you increase the quantity of the external activity. How does the system support this scenario?
Question 37
Dates
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
Question 38
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
Question 39
What is the reason for assigning billing plans in customer projects?
Question 40
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?