Question 21
To which object can you assign a factory calendar?
Question 22
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
Question 23
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
Question 24
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
Question 25
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.