Question 36
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
Question 37
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well.
Now, you increase the quantity of the external activity. How does the system support this scenario?
Now, you increase the quantity of the external activity. How does the system support this scenario?
Question 38
You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
Question 39
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.
Question 40
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
Premium Bundle
Newest C-TS412-1909 Exam PDF Dumps shared by BraindumpsPass.com for Helping Passing C-TS412-1909 Exam! BraindumpsPass.com now offer the updated C-TS412-1909 exam dumps, the BraindumpsPass.com C-TS412-1909 exam questions have been updated and answers have been corrected get the latest BraindumpsPass.com C-TS412-1909 pdf dumps with Exam Engine here: