Question 26

In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
  • Question 27

    What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
  • Question 28

    For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
  • Question 29

    Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
  • Question 30

    Project Structures
    You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?