Question 16

During a project phase, your customer raises some questions concerning parameters of the procurement type in the material master in the SAP ECC system.
Which of the following procurement type properties are valid? (Choose two)
  • Question 17

    When testing requirements planning in plant 1000, you receive the error message displayed below. Large numbers of materials are already available in plant 1000. As a first step in solving the problem, you activate requirements planning in the Customizing for plant 1000.

    What further tasks do you perform before you can use requirements planning in plant 1000 in SAP ECC?
  • Question 18

    Which of the following master data is necessary for the creation of material reservations for production orders?
  • Question 19

    Which of the following statements about consumption are correct? (Choose two)
  • Question 20

    From what point can you no longer use the Read PP master data in the production order?