Question 196
For the given information:

Activity A, duration 5 days, predecessors: none
Activity B, duration 3 days, predecessors: none
Activity C, duration 6 days, predecessors: A and B
Activity D, duration 7 days, predecessors: B
Activity E, duration 4 days, predecessors: C and D
Activity F, duration 2 days, predecessors: E and B
Which of the following shows the project's critical path?

Activity A, duration 5 days, predecessors: none
Activity B, duration 3 days, predecessors: none
Activity C, duration 6 days, predecessors: A and B
Activity D, duration 7 days, predecessors: B
Activity E, duration 4 days, predecessors: C and D
Activity F, duration 2 days, predecessors: E and B
Which of the following shows the project's critical path?
Question 197
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
Question 198
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Question 199
The cost baseline and project funding requirements are outputs of which process in Project Cost Management?
Question 200
The project manager is creating the communications management plan. Which group of inputs is required to begin?