Question 16

Under the FIDIC Silver Contract (edition 2017), which two of the answers provide for preconditions for certification and payment of the Interim Payment Certificate?
Choose all of the correct answers (multiple possibilities).
  • Question 17

    You are the Contract Manager of the Engineer in a condominium project under FIDIC Yellow Book (edition
    2017), with Time for Completion of 5 months.
    The Contractor received a Letter of Acceptance on 1 May 2022. The Contract Agreement was signed on 1 June 2022. The Contract Agreement states that the Commencement Date shall be notified by the Engineer, but it shall be no later than 14 days after the signing of the Contract Agreement, subject to the issuance of the construction permit.
    1 July 2022 is the first day the Engineer was at Site. On the same day, the Engineer issued a Notice to the Contractor that the Commencement Date shall be 15 July 2022. However, the construction permit was issued only on 1 August 2022.
    The Project was completed on 1 December 2022. After completion, the Employer submitted a claim for Delay Damages. Following consultations, the Parties could not reach agreement on the Commencement Date.
    What is the correct Commencement Date?
  • Question 18

    Which one of the following statements is correct regarding the Employer's Representative under the FIDIC Silver Book (edition 1999)?
  • Question 19

    Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?
  • Question 20

    If defects are identified during the Tests on Completion, which one of the following options is not available to the Parties under the Contract?