Question 26

Which two of the following statements are correct regarding Dispute under the FIDIC Red, Yellow, and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities)
  • Question 27

    For the FIDIC Red Book (both editions), the Contractor is required to submit a progress report monthly.
    When does the Contractor's reporting requirement end?
  • Question 28

    Under the FIDIC Red, Yellow, and Silver Books (both editions), the Contractor has a contractual obligation to submit a Value Engineering Proposal. Such proposal shall be prepared at the cost of the Employer. Are both these statements true or false?
  • Question 29

    If the Engineer is required to obtain the Employer's prior approval to issue determinations (including such requirement in the Particular Conditions) and such approval was not given by the Employer, what possible options are at stake for the Engineer to proceed? [1999 Edition] (2 correct answers apply) Choose all of the correct answers (multiple possibilities).
  • Question 30

    You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017).
    The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?