Question 91
An enterprise made a significant change to its business operating model that resulted in a new strategic direction. Which of the following should be reviewed FIRST to ensure IT congruence with the new business strategy?
Question 92
In a successful enterprise that is profitable in its marketplace and consistently growing in size, the non-IT workforce has grown by 50% in the last two years. The demand for IT staff in the marketplace is more than the supply, and the enterprise is losing staff to rival organizations. Due to the rapid growth, IT has struggled to keep up with the enterprise, and IT procedures and associated job roles are not well-defined. The MOST critical activity for reducing the impact caused by IT staff turnover is to:
Question 93
In software development, which of the following analysis is used to document the services and functions that have been accidentally left out, deliberately eliminated or still need to be developed?
Question 94
Which of the following should be done FIRST when concerns have been identified regarding the financial viability of a potential software supplier?
Question 95
Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team.
Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?
Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?