- Home
- APICS Certification
- CPIM-Part-2 Exam
- APICS.CPIM-Part-2.v2024-06-09.q56 Practice Test
Question 1
Which of the following is the fundamental difference between finite loading and other capacity planning approaches?
Correct Answer: D
Explanation
Finite loading is a capacity planning approach that considers adjustments to plans based on planned capacity utilization. It does not allow overloading of resources and schedules operations only when there is enough capacity available. Finite loading creates a more realistic schedule for the production processes than other approaches, such as infinite loading, that ignore the capacityconstraints and assume that the due dates of orders are absolute. Finite loading is not highly dependent on advanced computer software, although it can benefit from it. It is not only managed by shop floor supervisors, but also by planners and schedulers. It can use historical information, but it is not the only approach that can do so. Therefore, the fundamental difference between finite loading and other capacity planning approaches is that it considers adjustments to plans based on planned capacity utilization. References := CPIM Part 2 Exam Content Manual, Domain 6: Plan, Manage, and Execute Detailed Schedules, Section B: Schedule Production Activities, Subsection 1: Develop a detailed production schedule (p. 28)
Finite loading is a capacity planning approach that considers adjustments to plans based on planned capacity utilization. It does not allow overloading of resources and schedules operations only when there is enough capacity available. Finite loading creates a more realistic schedule for the production processes than other approaches, such as infinite loading, that ignore the capacityconstraints and assume that the due dates of orders are absolute. Finite loading is not highly dependent on advanced computer software, although it can benefit from it. It is not only managed by shop floor supervisors, but also by planners and schedulers. It can use historical information, but it is not the only approach that can do so. Therefore, the fundamental difference between finite loading and other capacity planning approaches is that it considers adjustments to plans based on planned capacity utilization. References := CPIM Part 2 Exam Content Manual, Domain 6: Plan, Manage, and Execute Detailed Schedules, Section B: Schedule Production Activities, Subsection 1: Develop a detailed production schedule (p. 28)
Question 2
Risk pooling would work best for items with:
Correct Answer: D
Explanation
Risk pooling is a strategy to reduce the total safety stock by aggregating the inventory of multiple items or locations. Risk pooling works best for items with high demand uncertainty and long lead times, because these items have higher variability and require more safety stock. By pooling the inventory, the variability of the total demand is reduced, and the safety stock can be lowered without increasing the risk of stockouts. References: CPIM Part 2 Exam Content Manual, Domain 5: Plan and Manage Inventory, Section
5.3: Inventory Management Policies and Objectives, p. 28.
Risk pooling is a strategy to reduce the total safety stock by aggregating the inventory of multiple items or locations. Risk pooling works best for items with high demand uncertainty and long lead times, because these items have higher variability and require more safety stock. By pooling the inventory, the variability of the total demand is reduced, and the safety stock can be lowered without increasing the risk of stockouts. References: CPIM Part 2 Exam Content Manual, Domain 5: Plan and Manage Inventory, Section
5.3: Inventory Management Policies and Objectives, p. 28.
Question 3
If all other factors remain the same, when finished goods inventory investment is increased, service levels typically will:
Correct Answer: C
Explanation
Finished goods inventory is a type of inventory that consists of the final products that are ready for sale to the customers. Finished goods inventory investment is the value of the finished goods inventory held by the company. Service level is a measure of customer satisfaction that indicates the percentage of customer orders that can be fulfilled from the available inventory. Service level typically will increase when finished goods inventory investment is increased, because more inventory means more ability to meet the customer demand.
However, the relationship between service level and finished goods inventory investment is not linear, but rather asymptotic. This means that service level will increase at a decreasing rate as finished goods inventory investment increases. In other words, the marginal benefit of increasing finished goods inventory investment will diminish as the service level approaches 100%. This is because there is a limit to how much inventory can improve the service level, and beyond a certain point, the additional inventory will not have a significant impact on customer satisfaction.
References: CPIM Exam Content Manual Version 7.0, Domain 5: Plan and Manage Inventory, Section 5.1:
Develop Inventory Plans, Subsection 5.1.2: Describe how to develop an inventory policy (page 44).
Finished goods inventory is a type of inventory that consists of the final products that are ready for sale to the customers. Finished goods inventory investment is the value of the finished goods inventory held by the company. Service level is a measure of customer satisfaction that indicates the percentage of customer orders that can be fulfilled from the available inventory. Service level typically will increase when finished goods inventory investment is increased, because more inventory means more ability to meet the customer demand.
However, the relationship between service level and finished goods inventory investment is not linear, but rather asymptotic. This means that service level will increase at a decreasing rate as finished goods inventory investment increases. In other words, the marginal benefit of increasing finished goods inventory investment will diminish as the service level approaches 100%. This is because there is a limit to how much inventory can improve the service level, and beyond a certain point, the additional inventory will not have a significant impact on customer satisfaction.
References: CPIM Exam Content Manual Version 7.0, Domain 5: Plan and Manage Inventory, Section 5.1:
Develop Inventory Plans, Subsection 5.1.2: Describe how to develop an inventory policy (page 44).
Question 4
Which of the following priority rules is most consistent with the objective of meeting due dates?
Correct Answer: D
Explanation
The priority rule that is most consistent with the objective of meeting due dates is slack time per operation.
Slack time per operation is a priority rule that assigns a priority index to each job based on the ratio of the remaining slack time to the remaining number of operations. Slack time is the difference between the due date and the expected completion time of a job. A lower ratio means a higher priority, as it indicates that the job has less slack time per operation and is more likely to be late. Slack time per operation is a dynamic priority rule, as it updates the priority index after each operation is completed. Slack time per operation can help minimize the number of tardy jobs and the average tardiness of jobs, as it gives preference to the jobs that are closer to their due dates and have more operations left.
First-come-first-served (FCFS) is not a priority rule that is consistent with the objective of meeting due dates.
FCFS is a priority rule that processes jobs in the order of their arrival or release times. FCFS is a simple and fair rule, but it ignores the processing times and due dates of jobs. FCFS can result in poor due date performance, as it can delay urgent or short jobs behind long or non-urgent jobs.
Shortest processing time (SPT) is not a priority rule that is consistent with the objective of meeting due dates.
SPT is a priority rule that processes jobs in ascending order of their processing times. SPT is an effective rule for minimizing the average flow time and work-in-process inventory of jobs, as it clears out small jobs quickly and reduces congestion in the system. However, SPT does not consider the due dates of jobs, and it can make long or urgent jobs late.
Fewest operations remaining is not a priority rule that is consistent with the objective of meeting due dates.
Fewest operations remaining is a priority rule that processes jobs in ascending order of their remaining number of operations. Fewest operations remaining is a rule that can reduce the variability and complexity of jobs, as it tends to complete jobs faster and reduce their flow times. However, fewest operations remaining does not take into account the slack times or due dates of jobs, and it can make urgent or short jobs late.
References := Priority Rules - Tripod, Dispatching rules - Oxford Reference, Sequencing Rules and Due-Date Assignments in a Job Shop - JSTOR
The priority rule that is most consistent with the objective of meeting due dates is slack time per operation.
Slack time per operation is a priority rule that assigns a priority index to each job based on the ratio of the remaining slack time to the remaining number of operations. Slack time is the difference between the due date and the expected completion time of a job. A lower ratio means a higher priority, as it indicates that the job has less slack time per operation and is more likely to be late. Slack time per operation is a dynamic priority rule, as it updates the priority index after each operation is completed. Slack time per operation can help minimize the number of tardy jobs and the average tardiness of jobs, as it gives preference to the jobs that are closer to their due dates and have more operations left.
First-come-first-served (FCFS) is not a priority rule that is consistent with the objective of meeting due dates.
FCFS is a priority rule that processes jobs in the order of their arrival or release times. FCFS is a simple and fair rule, but it ignores the processing times and due dates of jobs. FCFS can result in poor due date performance, as it can delay urgent or short jobs behind long or non-urgent jobs.
Shortest processing time (SPT) is not a priority rule that is consistent with the objective of meeting due dates.
SPT is a priority rule that processes jobs in ascending order of their processing times. SPT is an effective rule for minimizing the average flow time and work-in-process inventory of jobs, as it clears out small jobs quickly and reduces congestion in the system. However, SPT does not consider the due dates of jobs, and it can make long or urgent jobs late.
Fewest operations remaining is not a priority rule that is consistent with the objective of meeting due dates.
Fewest operations remaining is a priority rule that processes jobs in ascending order of their remaining number of operations. Fewest operations remaining is a rule that can reduce the variability and complexity of jobs, as it tends to complete jobs faster and reduce their flow times. However, fewest operations remaining does not take into account the slack times or due dates of jobs, and it can make urgent or short jobs late.
References := Priority Rules - Tripod, Dispatching rules - Oxford Reference, Sequencing Rules and Due-Date Assignments in a Job Shop - JSTOR
Question 5
When forecasting the demand for a product, the highest percentage of error will occur at the:
Correct Answer: D
Explanation
The question is about forecasting the demand for a product, and the options are different levels of aggregation or disaggregation. The highest percentage of error will occur at the most disaggregated level, which is the field warehouses. The field warehouses are the locations where the finished products are stored and delivered to the customers. The demand at the field warehouses is affected by various factors, such as customer preferences, seasonality, promotions, and competition. The demand at the field warehouses is also more volatile and uncertain than the demand at the higher levels of aggregation, such as the market segment or the central warehouse. Therefore, forecasting the demand at the field warehouses will have the highest percentage of error, which means that the forecast will deviate more from the actual demand.
The other options are not the levels where the highest percentage of error will occur. The master schedule is not a level of aggregation or disaggregation, but a plan that specifies the quantity and timing of finished products to be produced in a given period. The master schedule is based on the forecasted demand, the customer orders, and the production capacity. The master schedule does not have a percentage of error, but it may have a variance or deviation from the actual production output. The market segment is a level of aggregation that groups the customers or products based on their common characteristics or needs. The market segment is a higher level than the field warehouses, and it has less variability and uncertainty in demand.
Therefore, forecasting the demand at the market segment will have a lower percentage of error than forecasting at the field warehouses. The central warehouse is a level of aggregation that consolidates the inventory from different sources and distributes it to different destinations. The central warehouse is a higher level than the field warehouses, and it has less variability and uncertainty in demand. Therefore, forecasting the demand at the central warehouse will have a lower percentage of error than forecasting at the field warehouses.
The question is about forecasting the demand for a product, and the options are different levels of aggregation or disaggregation. The highest percentage of error will occur at the most disaggregated level, which is the field warehouses. The field warehouses are the locations where the finished products are stored and delivered to the customers. The demand at the field warehouses is affected by various factors, such as customer preferences, seasonality, promotions, and competition. The demand at the field warehouses is also more volatile and uncertain than the demand at the higher levels of aggregation, such as the market segment or the central warehouse. Therefore, forecasting the demand at the field warehouses will have the highest percentage of error, which means that the forecast will deviate more from the actual demand.
The other options are not the levels where the highest percentage of error will occur. The master schedule is not a level of aggregation or disaggregation, but a plan that specifies the quantity and timing of finished products to be produced in a given period. The master schedule is based on the forecasted demand, the customer orders, and the production capacity. The master schedule does not have a percentage of error, but it may have a variance or deviation from the actual production output. The market segment is a level of aggregation that groups the customers or products based on their common characteristics or needs. The market segment is a higher level than the field warehouses, and it has less variability and uncertainty in demand.
Therefore, forecasting the demand at the market segment will have a lower percentage of error than forecasting at the field warehouses. The central warehouse is a level of aggregation that consolidates the inventory from different sources and distributes it to different destinations. The central warehouse is a higher level than the field warehouses, and it has less variability and uncertainty in demand. Therefore, forecasting the demand at the central warehouse will have a lower percentage of error than forecasting at the field warehouses.
- Latest Upload
- 107SAP.C-S4CPB-2602.v2026-09-02.q7
- 108Cisco.700-805.v2026-09-02.q86
- 133MSSC.CLT-4.0.v2026-09-02.q43
- 116Fitness.NCSF-CPT.v2026-09-02.q18
- 127Google.Generative-AI-Leader.v2026-09-02.q77
- 139PECB.ISO-14001-Lead-Auditor.v2026-09-01.q39
- 126Google.GCP-DE.v2026-09-01.q27
- 137Cisco.300-820.v2026-09-01.q105
- 153Cisco.500-220.v2026-09-01.q72
- 234EXIN.PR2F.v2026-08-31.q524
[×]
Download PDF File
Enter your email address to download APICS.CPIM-Part-2.v2024-06-09.q56 Practice Test
