Question 11
What priority control technique is most appropriate for a firm using a cellular production system?
Correct Answer: C
Explanation
A priority control technique is a method of determining the sequence and timing of production orders in a manufacturing system. A priority control technique can be either push or pull, depending on whether the production orders are initiated by the upstream or downstream processes. A cellular production system is a process of manufacturing that organizes the machines and workers into self-contained cells that can produce different products efficiently and flexibly. A cellular production system is usually based on the principles of lean manufacturing and group technology, which aim to eliminate waste and improve quality.
A pull production activity control (PAC) is a priority control technique that is most appropriate for a firm using a cellular production system. A pull PAC is a method of controlling the flow of materials and work-in-progress in a manufacturing system by using signals from the downstream processes to trigger the release of production orders from the upstream processes. A pull PAC helps to reduce inventory, lead time, and overproduction, as well as to synchronize the production with the customer demand. A pull PAC can be implemented using various techniques, such as kanban cards, containers, or electronic signals.
A shortest processing time (SPT) rule is a priority control technique that assigns the highest priority to the production order that has the shortest processing time at each workstation. An SPT rule helps to minimize the average waiting time and flow time of the production orders, as well as to increase the utilization of the machines and workers. However, an SPT rule does not consider the due dates or the customer demand of the production orders, and may result in poor customer service or low delivery performance.
A distribution requirements planning (DRP) is a priority control technique that determines the quantity and timing of finished goods to be delivered to various distribution centers or customers. A DRP is based on the forecasted demand, the inventory status, and the transportation lead time of the finished goods. A DRP helps to optimize the inventory level, reduce stockouts, and improve customer service. However, a DRP is not suitable for a cellular production system, as it does not control the flow of materials and work-in-progress within the manufacturing system.
A push production activity control (PAC) is a priority control technique that initiates the production orders based on the master production schedule or the forecasted demand from the upstream processes. A push PAC releases the production orders in batches or lots, regardless of the capacity or status of the downstream processes. A push PAC may result in high inventory, long lead time, and overproduction, as well as low flexibility and responsiveness to customer demand. A push PAC is not compatible with a cellular production system, as it contradicts the principles of lean manufacturing and group technology. References: CPIM Exam Content Manual Version 7.0, Domain 6: Plan, Manage, and Execute Detailed Schedules, Section 6.1: Detailed Scheduling Concepts, p. 36; Cellular manufacturing; [Production Activity Control].
A priority control technique is a method of determining the sequence and timing of production orders in a manufacturing system. A priority control technique can be either push or pull, depending on whether the production orders are initiated by the upstream or downstream processes. A cellular production system is a process of manufacturing that organizes the machines and workers into self-contained cells that can produce different products efficiently and flexibly. A cellular production system is usually based on the principles of lean manufacturing and group technology, which aim to eliminate waste and improve quality.
A pull production activity control (PAC) is a priority control technique that is most appropriate for a firm using a cellular production system. A pull PAC is a method of controlling the flow of materials and work-in-progress in a manufacturing system by using signals from the downstream processes to trigger the release of production orders from the upstream processes. A pull PAC helps to reduce inventory, lead time, and overproduction, as well as to synchronize the production with the customer demand. A pull PAC can be implemented using various techniques, such as kanban cards, containers, or electronic signals.
A shortest processing time (SPT) rule is a priority control technique that assigns the highest priority to the production order that has the shortest processing time at each workstation. An SPT rule helps to minimize the average waiting time and flow time of the production orders, as well as to increase the utilization of the machines and workers. However, an SPT rule does not consider the due dates or the customer demand of the production orders, and may result in poor customer service or low delivery performance.
A distribution requirements planning (DRP) is a priority control technique that determines the quantity and timing of finished goods to be delivered to various distribution centers or customers. A DRP is based on the forecasted demand, the inventory status, and the transportation lead time of the finished goods. A DRP helps to optimize the inventory level, reduce stockouts, and improve customer service. However, a DRP is not suitable for a cellular production system, as it does not control the flow of materials and work-in-progress within the manufacturing system.
A push production activity control (PAC) is a priority control technique that initiates the production orders based on the master production schedule or the forecasted demand from the upstream processes. A push PAC releases the production orders in batches or lots, regardless of the capacity or status of the downstream processes. A push PAC may result in high inventory, long lead time, and overproduction, as well as low flexibility and responsiveness to customer demand. A push PAC is not compatible with a cellular production system, as it contradicts the principles of lean manufacturing and group technology. References: CPIM Exam Content Manual Version 7.0, Domain 6: Plan, Manage, and Execute Detailed Schedules, Section 6.1: Detailed Scheduling Concepts, p. 36; Cellular manufacturing; [Production Activity Control].
Question 12
An organization has seen inventory increase every month for the past year and financial performance has net met expectations. Which of the following processes would mostappropriately address correctingthe problem?
Correct Answer: B
Explanation
Sales and operations planning (S&OP) is a process that aligns the sales plan, the production plan, the inventory plan, and the financial plan to achieve the business objectives. S&OP helps to balance supply and demand, optimize resources, reduce inventory costs, and improve customer service. S&OP is done on an aggregate or family level, and covers a sufficient span of time to make sure that the necessary resources will be available. S&OP also involves regular reviews and updates of the plans based on the changes in the market and the company's performance.
Business planning is a process that defines the long-term vision, mission, goals, and strategies of the organization. Business planning provides the direction and framework for the operational plans, but does not address the specific issues of inventory management and financial performance.
Detailed material planning is a process that determines the quantity and timing of material requirements for each item or component in the production plan. Detailed material planning is based on the master schedule, which is derived from the S&OP. Detailed material planning does not address the alignment of sales and operations at an aggregate level.
Master scheduling is a process that translates the S&OP into a detailed plan for each product or service in a specific time period. Master scheduling specifies the quantityand timing of finished goods to be produced or delivered to meet the demand. Master scheduling is dependent on the S&OP, and does not address the coordination of sales and operations at an aggregate level.
References:
APICS Exam Handbook, page 12
CPIM Part 1 Study Guide, page 19
CPIM Part 2 Study Guide, page 17
Sales and Operations Planning (S&OP) 101| Smartsheet
Sales, Inventory & Operations Planning - What It Is and How to Operate
Sales and operations planning (S&OP) is a process that aligns the sales plan, the production plan, the inventory plan, and the financial plan to achieve the business objectives. S&OP helps to balance supply and demand, optimize resources, reduce inventory costs, and improve customer service. S&OP is done on an aggregate or family level, and covers a sufficient span of time to make sure that the necessary resources will be available. S&OP also involves regular reviews and updates of the plans based on the changes in the market and the company's performance.
Business planning is a process that defines the long-term vision, mission, goals, and strategies of the organization. Business planning provides the direction and framework for the operational plans, but does not address the specific issues of inventory management and financial performance.
Detailed material planning is a process that determines the quantity and timing of material requirements for each item or component in the production plan. Detailed material planning is based on the master schedule, which is derived from the S&OP. Detailed material planning does not address the alignment of sales and operations at an aggregate level.
Master scheduling is a process that translates the S&OP into a detailed plan for each product or service in a specific time period. Master scheduling specifies the quantityand timing of finished goods to be produced or delivered to meet the demand. Master scheduling is dependent on the S&OP, and does not address the coordination of sales and operations at an aggregate level.
References:
APICS Exam Handbook, page 12
CPIM Part 1 Study Guide, page 19
CPIM Part 2 Study Guide, page 17
Sales and Operations Planning (S&OP) 101| Smartsheet
Sales, Inventory & Operations Planning - What It Is and How to Operate
Question 13
The most appropriate production output reporting method for repetitive manufacturing is:
Correct Answer: D
Explanation
The most appropriate production output reporting method for repetitive manufacturing is backflush. Repetitive manufacturing is a production system where the same or similar products are produced in large quantities or in a continuous flow1. Backflush is a method of reporting output and consumption of materials at the end of the production process, rather than at each operation or stage2. Backflush can simplify and streamline the production output reporting process, as it eliminates the need for tracking and recording each individual transaction or movement of materials and components. Backflush can also reduce the paperwork, errors, and costs associated with production output reporting2.
The other options are not as appropriate as backflush for repetitive manufacturing. Operation-by-operation is a method of reporting output and consumption of materials at each operation or stage of the production process3. This method can provide more detailed and accurate information about the production performance and costs, but it can also be more complex and time-consuming, as itrequires tracking and recording each individual transaction or movement of materials and components. Count point is a method of reporting output and consumption of materials at selected points or milestones in the production process4. This method can provide a balance between detail and simplicity, but it can also introduce errors or discrepancies, as it requires estimating or extrapolating the output and consumption of materials between the count points. Job tickets are documents that record the time, materials, and costs associated with a specific job or order5. This method can provide more flexibility and customization, but it can also be more suitable for job shop or batch production systems, where different products are produced in small quantities or on demand.
References : Repetitive Manufacturing: Definition & Benefits; Backflush Costing: Definition & Example; Operation by Operation Reporting - ERP Software Blog; Count Point Reporting - ERP Software Blog; Job Ticket Definition.
The most appropriate production output reporting method for repetitive manufacturing is backflush. Repetitive manufacturing is a production system where the same or similar products are produced in large quantities or in a continuous flow1. Backflush is a method of reporting output and consumption of materials at the end of the production process, rather than at each operation or stage2. Backflush can simplify and streamline the production output reporting process, as it eliminates the need for tracking and recording each individual transaction or movement of materials and components. Backflush can also reduce the paperwork, errors, and costs associated with production output reporting2.
The other options are not as appropriate as backflush for repetitive manufacturing. Operation-by-operation is a method of reporting output and consumption of materials at each operation or stage of the production process3. This method can provide more detailed and accurate information about the production performance and costs, but it can also be more complex and time-consuming, as itrequires tracking and recording each individual transaction or movement of materials and components. Count point is a method of reporting output and consumption of materials at selected points or milestones in the production process4. This method can provide a balance between detail and simplicity, but it can also introduce errors or discrepancies, as it requires estimating or extrapolating the output and consumption of materials between the count points. Job tickets are documents that record the time, materials, and costs associated with a specific job or order5. This method can provide more flexibility and customization, but it can also be more suitable for job shop or batch production systems, where different products are produced in small quantities or on demand.
References : Repetitive Manufacturing: Definition & Benefits; Backflush Costing: Definition & Example; Operation by Operation Reporting - ERP Software Blog; Count Point Reporting - ERP Software Blog; Job Ticket Definition.
Question 14
The production plan relates to a firm's financial planning because it is used to:
Correct Answer: D
Explanation
The production plan is a statement of the resources needed to meet the aggregate demand plan over a medium-term horizon. The production plan is the output of the supply planning step in the sales and operations planning (S&OP) process. The production plan relates to a firm's financial planning because it is used to identify future cash needs. Cash needs are the amount of money that a firm requires to operate and grow its business. Cash needs can be influenced by various factors, such as sales revenue, cost of goods sold, operating expenses, capital expenditures, inventory levels, accounts receivable, accounts payable, and taxes. The production plan can help to estimate the cash inflows and outflows associated with these factors, and to determine the optimal balance between them. The production plan can also help to identify the potential sources and uses of cash, such as borrowing, investing, or paying dividends. By identifying future cash needs, the production plan can help to improve the firm's liquidity, profitability, and solvency.
References: CPIM Exam Content Manual Version 7.0, Domain 4: Plan and Manage Supply, Section 4.1:
Develop Supply Plans, Subsection 4.1.2: Describe how to develop a production plan (page 36).
The production plan is a statement of the resources needed to meet the aggregate demand plan over a medium-term horizon. The production plan is the output of the supply planning step in the sales and operations planning (S&OP) process. The production plan relates to a firm's financial planning because it is used to identify future cash needs. Cash needs are the amount of money that a firm requires to operate and grow its business. Cash needs can be influenced by various factors, such as sales revenue, cost of goods sold, operating expenses, capital expenditures, inventory levels, accounts receivable, accounts payable, and taxes. The production plan can help to estimate the cash inflows and outflows associated with these factors, and to determine the optimal balance between them. The production plan can also help to identify the potential sources and uses of cash, such as borrowing, investing, or paying dividends. By identifying future cash needs, the production plan can help to improve the firm's liquidity, profitability, and solvency.
References: CPIM Exam Content Manual Version 7.0, Domain 4: Plan and Manage Supply, Section 4.1:
Develop Supply Plans, Subsection 4.1.2: Describe how to develop a production plan (page 36).
Question 15
Which of the following conditions is required for an effective single-sourcing relationship?
Correct Answer: C
Explanation
An effective single-sourcing relationship requires that the organizations must be mutually dependent. This means that both the customer and the supplier rely on each other for their success and benefit from the partnership. Mutual dependence can foster trust, collaboration, communication, innovation, and problem-solving between the parties. It can also reduce the risks of supply disruptions, quality issues, price fluctuations, and contract breaches. Mutual dependence can be achieved by aligning the goals, values, and strategies of the organizations, as well as by sharing information, resources, and risks. Demand for the customer's products does not have to be stable for a single-sourcing relationship to work. In fact, single sourcing can help the customer cope with demand variability by ensuring a consistent supply of goods or services from the supplier. The supplier does not have to offer the lowest price per unit for a single-sourcing relationship to be effective. The customer may choose a single supplier based on other factors, such as quality, delivery, innovation, or reputation. The price per unit may not reflect the total cost of ownership, which includes other costs such as transportation, inventory, maintenance, and warranty. The organizations do not have to be located close to each other for a single-sourcing relationship to be successful. With advances in technology and logistics, distance is not a major barrier for communication and coordination between the customer and the supplier. Moreover, single sourcing can reduce the complexity of managing multiple suppliers across different locations. References := What Is Single Sourcing? (Plus Benefits and 7 Examples), Single Sourcing Vs Sole Sourcing Sourcing | CIPS, What Is Single Sourcing In Procurement And Why Is It Important?
An effective single-sourcing relationship requires that the organizations must be mutually dependent. This means that both the customer and the supplier rely on each other for their success and benefit from the partnership. Mutual dependence can foster trust, collaboration, communication, innovation, and problem-solving between the parties. It can also reduce the risks of supply disruptions, quality issues, price fluctuations, and contract breaches. Mutual dependence can be achieved by aligning the goals, values, and strategies of the organizations, as well as by sharing information, resources, and risks. Demand for the customer's products does not have to be stable for a single-sourcing relationship to work. In fact, single sourcing can help the customer cope with demand variability by ensuring a consistent supply of goods or services from the supplier. The supplier does not have to offer the lowest price per unit for a single-sourcing relationship to be effective. The customer may choose a single supplier based on other factors, such as quality, delivery, innovation, or reputation. The price per unit may not reflect the total cost of ownership, which includes other costs such as transportation, inventory, maintenance, and warranty. The organizations do not have to be located close to each other for a single-sourcing relationship to be successful. With advances in technology and logistics, distance is not a major barrier for communication and coordination between the customer and the supplier. Moreover, single sourcing can reduce the complexity of managing multiple suppliers across different locations. References := What Is Single Sourcing? (Plus Benefits and 7 Examples), Single Sourcing Vs Sole Sourcing Sourcing | CIPS, What Is Single Sourcing In Procurement And Why Is It Important?
- Latest Upload
- 109SAP.C-S4CPB-2602.v2026-09-02.q7
- 109Cisco.700-805.v2026-09-02.q86
- 133MSSC.CLT-4.0.v2026-09-02.q43
- 118Fitness.NCSF-CPT.v2026-09-02.q18
- 132Google.Generative-AI-Leader.v2026-09-02.q77
- 139PECB.ISO-14001-Lead-Auditor.v2026-09-01.q39
- 126Google.GCP-DE.v2026-09-01.q27
- 159Cisco.300-820.v2026-09-01.q105
- 153Cisco.500-220.v2026-09-01.q72
- 239EXIN.PR2F.v2026-08-31.q524
[×]
Download PDF File
Enter your email address to download APICS.CPIM-Part-2.v2024-06-09.q56 Practice Test