Question 51

By using following product tree, how many Ks are needed to make 200Xs and 150 Ys?
  • Question 52

    The concept in which to preplan and generate schedules but instead to react to the final customer order and produce only what is needed to satisfy demand and then only when it is needed, is known as:
  • Question 53

    A work center consists of four machines and is operated 8 hours per day for 5 days a week. Historically, the utilization has been 85% and the efficiency 110%.what is the rated capacity?
  • Question 54

    For each product
    how the product is made.
  • Question 55

    The cost associated with checking and auditing quality in the organization is called: