Question 1
Which of the following statements describes a continuous replenishment strategy in a retail environment?
Question 2
An operations manager wants to measure variability in the delivery time of insurance policies to clients. Which of the following quality tools most appropriately would show the level of variability?
Question 3
Which of the following processes ensures that functional plans are consistent?
Question 4
Customer demand is 120 units per week. The company works on a 9-hour shift per day, 5-day per week basis. Each shift has a ½-hour lunch break and two 15-minute coffee breaks. The cycle time is 12 minutes.
To meet demand, production must occur at the rate of one unit every:
To meet demand, production must occur at the rate of one unit every:
Question 5
The most appropriate frequency for the sales and operations planning process typically is: