Question 61

Most managers in your company consider the efforts of your test team valuable, while others see comprehensive testing as an unnecessary cost overhead to the SDLC.
What action could the Test Manager take to quantify the value of testing to the organization? [3]
  • Question 62

    Which of the following Is the common set of information to be produced in a test estimate''
  • Question 63

    A project to replace an old sales and merchandising system with a new version based on modern platforms, will use an Agile lifecycle with iterations of fixed length.
    The project objectives include:
    * Delivery within 6 months of the start of the first iteration, in 3 releases, to be accomplished by a team that will contain all resources deemed necessary to achieve this
    * Quality of delivered product to meet customer acceptance criteria
    A test objective, derived from discussion with the customers, has been set as follows:
    "Each release shall deliver usability that is better than that of the previous system for the equivalent functionality" Which S.M.A.R.T. criteria are met by this objective?
    * Specific
    * Measurable
    * Achievable
    * Relevant
    * Timely
  • Question 64

    You are the Test Manager for a software house (SoftTech), who provide a core banking product to retail banks around the world to enable their customers to process payments via the Internet and telephone banking.
    Your current project is to integrate SoftTech's core banking product with Welsh Bank's existing bank systems. However, Welsh Bank's systems are maintained by experienced developers and are poorly documented.
    Welsh Bank has stated that this project must comply with Financial Conduct Authority (FCA) regulatory banking standards.
    A specification for the 10 interfaces to Welsh Bank's existing systems has been produced by SoftTech's development team.
    You have been asked to plan and conduct reviews for the system integration and support documentation of all the systems. Which of the following is the BEST approach for this project?
    SELECT ONE OPTION
  • Question 65

    You just handed over the Defect Accepted and Deferred report to your Maintenance team.
    Which testing activity are you performing? [1]