Question 76

Within the projects, a master test plan and phase test plan will be used. Following is a list of characteristics applicable for test plans:
a.Any deviation from the procedures described in the test
b.strategy document
c.The overall estimated costs, timescales and resource
d.requirements
e.A detailed schedule of testing activities
f.The development deliverables to be tested
g.Which test staff members (names) will be involved and when
h.Level of requirements coverage achieved
Which TWO of the above mentioned characteristics relate to the phase test plan? 1 credit
  • Question 77

    Instead of having an independent test team within the company, the company is considering to outsource testing. What are THREE key challenges that are typical for outsourcing? 1 credit
  • Question 78

    Your team has decided that they will build their own test management tool This will allow them to link the requirements and test cases together providing full traceability It will also allow them to create fully customized reporting and color-coded dashboards They have estimated the time required to create the new tool and the cost These fit within the project schedule and budget What other consideration should be taken before this decision is made?
  • Question 79

    The Test Manager must assemble team members that have which of the following characteristics? [1]
  • Question 80

    Your team has been given the following test objective Ensure that the users are happier with this version than they were with the last version?
    What is wrong with the way this is defined?