Question 11

An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
  • Question 12

    What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
  • Question 13

    Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.
  • Question 14

    Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.
  • Question 15

    What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.