Question 16

To which object can you assign a factory calendar?
  • Question 17

    You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
  • Question 18

    Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
  • Question 19

    What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
  • Question 20

    You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?