Question 11
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
                        
                    
                    Question 12
What is the reason for assigning billing plans in customer projects?
                        
                    
                    Question 13
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
                        
                    
                    Question 14
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
                        
                    
                    You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
Question 15
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?
                        
                    
                     
            
Correct answer is B