Question 31

You have saved a network and activities with assigned material components. As soon as you release the network, you receive the error message "Business transaction cannot be carried out". What could be the reason for this error message?
  • Question 32

    Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.
  • Question 33

    You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct answers to this question
  • Question 34

    Your customer has created networks with internal activities and generated capacity requirements. Now,
    they want to analyze the capacity requirements of their project. Which report do you recommend?
  • Question 35

    How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.