Question 61
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.
Note : there are 2 correct answers for this question.
Question 62
In your logistics project you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
Question 63
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
Question 64
Which object is used to allocate the costs from a claim to the project structure?
Question 65
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.